What tools or techniques are necessary to create the project management plan?
Match the process with its corresponding Process Group:
What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives'?
Which of the following is used as input to prepare a cost management plan?
The milestone list is an input to which process from the Planning Process Group?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Project contracts generally fall into which of the following three broad categories?
The project scope statement and resource calendars are inputs to which Project Time Management process?
Perform Quantitative Analysis focuses on:
In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
What is the responsibility of the project manager and the functional manager respectively?
What causes replanning of the project scope?
Which of the following is an information gathering technique in Identify Risks?
Which of the following tools and techniques is used in the Verify Scope process?
Which process should be conducted from the project inception through completion?
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
In a weak matrix, the project managers role is:
Which process involves identifying and documenting the logical relationships between project activities?
Which Process Group contains those processes performed to define a new project?
During which process would stakeholders provide formal acceptance of the completed project scope?
Labor, materials, equipment, and supplies are examples of:
A project team member identifies a possibility......the team member's idea?
A project team member identifies a possibility of increasing project performance by adopting an innovative approach to a proposed solution. This also will save resources for the company and increase stakeholder satisfaction.
How should the project manager evaluate the team member's idea?
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
A method to manage stakeholder expectations in the scope statement is to clearly:
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?
A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?
When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?
Match the influence with its corresponding category of influence.
Make-or-buy analysis is a tool and technique of which process?
An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?
Which of the following are components of the technical project management skill?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
Which is the correct hierarchy in a project environment, from most to least Inclusive?
A project lead asks the team to create a work breakdown structure (WBS) of the project's scope. The team is confused about how far they should break down the scope.
What should the project lead tell the team?
Select three elements that apply to agile/ adaptive environments
What is one of the main purposes of the project charter?
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
Which of the following are processes associated with Project Cost Management?
Which element does a project charter contain?
A project manager called for a team meeting...................method did the team use
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?
A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?