Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 2 out of 8 pages
Viewing questions 51-100 out of questions
Questions # 51:

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?

Options:

A.

Iterative


B.

On-demand


C.

Interactive


D.

Quality


Expert Solution
Questions # 52:

In an agile or adaptive environment. when should risk be monitored and prioritized?

Options:

A.

Only during the initiation and Closing phases


B.

During the initiation and Planning phases


C.

During each iteration as the project progresses


D.

Throughout the Planning process group and retrospective meeting


Expert Solution
Questions # 53:

The Perform Integrated Change Control process occurs in which Process Group?

Options:

A.

Initiating


B.

Executing


C.

Monitoring and Controlling


D.

Planning


Expert Solution
Questions # 54:

Development of the benefits management plan occurs in which stage of the project life cycle?

Options:

A.

Starting the project


B.

Organizing the project


C.

Completing pre-project work


D.

Executing the product


Expert Solution
Questions # 55:

What can a requirements traceability matrix enable regardless of the project methodology being used?

Options:

A.

Creation of a solid business case


B.

Investigation of the viability of a new product


C.

Identification of missing and superfluous requirements


D.

Evaluation of solution and system performance


Expert Solution
Questions # 56:

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

Options:

A.

Less time spent on defining scope early on


B.

More time spent on defining scope early on


C.

Less time spent on scope management process


D.

Project scope management is the same in all projects


Expert Solution
Questions # 57:

In which process might a project manager use risk reassessment as a tool and technique?

Options:

A.

Perform Qualitative Risk Analysis


B.

Monitor and Control Risk


C.

Monitor and Control Project Work


D.

Plan Risk Responses


Expert Solution
Questions # 58:

A project manager needs to develop a product roadmap. Which artifact category is a product roadmap?

Options:

A.

Report artifact


B.

Strategic artifact


C.

Baseline artifact


D.

Plan artifact


Expert Solution
Questions # 59:

Which of the following is an example of an internal factor that influences the outcome of the project?

Options:

A.

Legal restrictions


B.

Financial considerations


C.

Commercial database


D.

Geographic distribution of facilities


Expert Solution
Questions # 60:

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

Options:

A.

Plan Resource Management


B.

Estimate Activity Resources Communications


C.

Estimate Costs


D.

Acquire Resources


Expert Solution
Questions # 61:

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Options:

A.

Control Schedule


B.

Define Activities


C.

Develop Schedule


D.

Estimate Activity Resources


Expert Solution
Questions # 62:

When is a Salience Model used?

Options:

A.

In a work breakdown structure (WBS)


B.

During quality assurance


C.

In stakeholder analysis


D.

During quality control (QC)


Expert Solution
Questions # 63:

Who is responsible for initiating a project?

Options:

A.

Project sponsor


B.

Project manager


C.

Program manager


D.

Project management office (PMO)


Expert Solution
Questions # 64:

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

Options:

A.

Work performance reports


B.

Assumptions logs


C.

Network diagrams


D.

Academic studies


Expert Solution
Questions # 65:

The Monitoring and Controlling Process Group includes processes that:

Options:

A.

Establish the scope, objectives, and course of action of a project,


B.

Define a new project or a new phase of an existing project.


C.

Track, review, and regulate the progress and performance of a project.


D.

Complete the work defined in the project management plan.


Expert Solution
Questions # 66:

What is the equation to calculate cost variance (CV)?

Options:

A.

CV = EV / BAC


B.

CV = EV - AC


C.

CV = EV - BAC


D.

CV = EV / AC


Expert Solution
Questions # 67:

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

Options:

A.

Expert judgment.


B.

Analytical techniques.


C.

Earned value management.


D.

Group decision-making techniques.


Expert Solution
Questions # 68:

The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager ' s disposal?

Options:

A.

Resource leveling and fast tracking


B.

Fast tracking and crashing


C.

Crashing and applying leads and lags


D.

Scheduling tools and applying leads and lags


Expert Solution
Questions # 69:

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers


B.

Business partners


C.

Customers or sponsors


D.

Subject matter experts


Expert Solution
Questions # 70:

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

Options:

A.

-8


B.

425


C.

1.4


D.

8


Expert Solution
Questions # 71:

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.


B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.


C.

a recognized standard for the project management profession.


D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.


Expert Solution
Questions # 72:

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client ' s overall business objectives.


B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.


C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.


D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.


Expert Solution
Questions # 73:

Which of the following strategic considerations often results in project authorization?

Options:

A.

Customer requests and/or issue resolution


B.

Stakeholder expectations and/or strategic opportunity (business need)


C.

Technological advancement and/or senior executive request


D.

Market demand and/or legal requirements


Expert Solution
Questions # 74:

Which document describes the necessary information to determine if a project is worth the required investment?

Options:

A.

Cost baseline


B.

Service level agreement


C.

Memorandum of understanding


D.

Business case


Expert Solution
Questions # 75:

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

Options:

A.

Monitor and Control Risks


B.

Plan Risk Management


C.

Perform Qualitative Risk Analysis


D.

Perform Quantitative Risk Analysis


Expert Solution
Questions # 76:

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

Options:

A.

triangular distribution


B.

tornado diagram


C.

beta distribution


D.

fishbone diagram


Expert Solution
Questions # 77:

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

Options:

A.

Plan Risk Responses


B.

Manage Stakeholder Expectations


C.

Define Scope


D.

Report Performance


Expert Solution
Questions # 78:

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

Options:

A.

cultural differences of team members


B.

possibility of communication misunderstandings


C.

costs associated with travel


D.

costs associated with technology


Expert Solution
Questions # 79:

Co-location is a tool and technique of:

Options:

A.

Develop Human Resource Plan.


B.

Manage Project Team.


C.

Develop Project Team.


D.

Acquire Project Team.


Expert Solution
Questions # 80:

It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?

Options:

A.

Pareto chart


B.

Regression analysis


C.

Statistical sampling


D.

Automated testing tools


Expert Solution
Questions # 81:

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

Options:

A.

Monitor and Control Project Work


B.

Direct and Manage Project Work


C.

Close Project or Phase


D.

Perform Integrated Change Control


Expert Solution
Questions # 82:

Which of these is true project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects


B.

Project Integration Management and Expert Judgement are mutually exclusive


C.

Project Integration Management is the responsibility of the project manager


D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero


Expert Solution
Questions # 83:

Tools and techniques used in Direct and Manage Project Work include:

Options:

A.

Process analysis and expert judgment


B.

Analytical techniques and a project management information system


C.

Performance reviews and meetings


D.

Expert judgment and meetings


Expert Solution
Questions # 84:

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

Options:

A.

Analogous


B.

Parametric


C.

Bottom-up


D.

Top-down


Expert Solution
Questions # 85:

When would resource leveling be applied to a schedule model?

Options:

A.

Before constraints have been identified


B.

Before it has been analyzed by the critical path method


C.

After it has been analyzed by the critical path method


D.

After critical activities have been removed from the critical path


Expert Solution
Questions # 86:

When cost variance is negative and schedule variance is positive, the project is:

Options:

A.

under budget and behind schedule.


B.

over budget and ahead of schedule.


C.

on schedule.


D.

complete; all planned values have been earned.


Expert Solution
Questions # 87:

A business manager wants to start a project to launch a new product. How should the manager initiate the project?

Options:

A.

Ask a small team to produce a prototype of the product before full-scale development.


B.

Assign a project manager to the project and ask them to document the project scope.


C.

Prepare a detailed business case to document project objectives and success criteria.


D.

Discuss the project requirements with the team for alternative products in the market.


Expert Solution
Questions # 88:

Which of the following is an output of Define Scope?

Options:

A.

Project scope statement


B.

Project charter


C.

Project plan


D.

Project schedule


Expert Solution
Questions # 89:

Which technique helps to determine the risks that have the most potential impact on a project?

Options:

A.

Cost risk simulation analysis


B.

Expected monetary value analysis


C.

Modeling and simulation


D.

Sensitivity analysis


Expert Solution
Questions # 90:

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

Options:

A.

Transfer


B.

Share


C.

Avoid


D.

Accept


Expert Solution
Questions # 91:

A stakeholder asked the project manager to add an additional feature to the project scope. The project manager is unsure whether the project budget will allow this additional scope.

What component of the project management plan should the project manager reference to determine whether the budget will allow a new feature to be added?

Options:

A.

Risk management plan


B.

Cost estimate


C.

Risk register


D.

Cost management plan


Expert Solution
Questions # 92:

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

Options:

A.

Critical path method


B.

Variance analysis


C.

Schedule compression


D.

Schedule comparison bar charts


Expert Solution
Questions # 93:

Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)

Options:

A.

Current state analysis


B.

Facilitated workshops


C.

Scheduled interviews


D.

Shop floor observation


E.

Brainstorming sessions


Expert Solution
Questions # 94:

Which schedule network analysis technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning


B.

Fast tracking


C.

Critical chain method


D.

Rolling wave planning


Expert Solution
Questions # 95:

As the project progresses, which of the following is routinely collected from the project activities?

Options:

A.

Communication management activities


B.

Change requests


C.

Configuration verification and audit


D.

Work performance information


Expert Solution
Questions # 96:

A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?

Options:

A.

Identify Stakeholders


B.

Plan Stakeholder Engagement


C.

Manage Stakeholder Engagement


D.

Monitor Slakeholder Engagement


Expert Solution
Questions # 97:

Stakeholder satisfaction should be managed as a key project:

Options:

A.

Benefit


B.

Initiative


C.

Objective


D.

Process


Expert Solution
Questions # 98:

What important leadership quality/qualities should project managers possess?

Options:

A.

Skills and behaviors related to specific domains of project management


B.

Skills and behaviors needed to guide a team and help an organization reach its goals


C.

Industry expertise that helps to better deliver business outcomes


D.

Industry and organizational expertise that enhances performance


Expert Solution
Questions # 99:

Which are the competing constraints that project manager should address when tailoring a project?

Options:

A.

Cost, scope, schedule


B.

Sponsorship, risk, quality


C.

Schedule, sponsorship, scope


D.

Resources, Quality, Communication


Expert Solution
Questions # 100:

For what project management process is work performance information an output?

Options:

A.

Implement Risk Responses


B.

Plan Stakeholder Engagement


C.

Monitor Stakeholder Engagement


D.

Plan Quality Management


Expert Solution
Viewing page 2 out of 8 pages
Viewing questions 51-100 out of questions