New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 2 out of 8 pages
Viewing questions 51-100 out of questions
Questions # 51:

The following chart contains information about the tasks in a project.

Question # 51

Based on the chart, what is the schedulevariance (SV) for Task 8?

Options:

A.

-2,000


B.

-1,000


C.

1,000


D.

2,000


Expert Solution
Questions # 52:

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid


B.

Power/influence grid


C.

Power/interest grid


D.

Salience model


Expert Solution
Questions # 53:

An input to the Perform Integrated Change Control process is:

Options:

A.

expert judgment


B.

seller proposals


C.

the project charter


D.

the project management plan


Expert Solution
Questions # 54:

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

Options:

A.

Identify Risks


B.

Plan Risk Management


C.

Perform Qualitative Risk Analysis


D.

Perform Quantitative Risk Analysis


Expert Solution
Questions # 55:

The following is a network diagram for a project.

Question # 55

The free float for Activity H is how many days?

Options:

A.

4


B.

5


C.

10


D.

11


Expert Solution
Questions # 56:

The component of the risk management plan that documents how risk activities will be recorded is called:

Options:

A.

tracking


B.

scoping


C.

timing


D.

defining


Expert Solution
Questions # 57:

The primary benefit of the Plan Schedule Management process is that it:

Options:

A.

provides guidance to identify time or schedule challenges within the project.


B.

tightly links processes to create a seamless project schedule.


C.

guides how the project schedule will be managed throughout the project.


D.

creates an overview of all activities broken down into manageable subsections.


Expert Solution
Questions # 58:

A project manager who communicates to the project team though email is using which type of communication?

Options:

A.

Formal


B.

Informal r


C.

Horizontal


D.

Unofficial


Expert Solution
Questions # 59:

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

Options:

A.

Continuous


B.

Discrete


C.

Regulated


D.

Arbitrary


Expert Solution
Questions # 60:

High-level project risks are included in which document?

Options:

A.

Business case


B.

Risk breakdown structure


C.

Project charter


D.

Risk register


Expert Solution
Questions # 61:

When closing a project or phase, part of the process may require the use of which type of analysis?

Options:

A.

Reserve analysis


B.

Regression analysis


C.

Document analysis


D.

Product analysis


Expert Solution
Questions # 62:

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

Options:

A.

Result


B.

Product


C.

Service


D.

Improvement


Expert Solution
Questions # 63:

An input to the Control Quality process is:

Options:

A.

Activity attributes


B.

Quality control measurements


C.

Enterprise environmental factors


D.

Deliverables


Expert Solution
Questions # 64:

Which items are components of a project management plan?

Options:

A.

Change management plan, process improvement plan, and scope management plan


B.

Agreements, procurement management plan, and work performance information


C.

Schedule management plan, project schedule, and resource calendars


D.

Scope baseline, project statement of work, and requirements traceability matrix


Expert Solution
Questions # 65:

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

Options:

A.

lead


B.

lag


C.

mandatory dependency


D.

internal dependency


Expert Solution
Questions # 66:

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management


B.

Identify Stakeholders


C.

Manage Stakeholder Engagement


D.

Control Stakeholder Engagement


Expert Solution
Questions # 67:

A graphic display of project team members and their reporting relationships is known as a:

Options:

A.

Resource calendar.


B.

Project organization chart.


C.

Resource breakdown structure (RBS).


D.

Responsibility assignment matrix (RAM).


Expert Solution
Questions # 68:

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03


B.

0.06


C.

0.10


D.

0.50


Expert Solution
Questions # 69:

Which Project Time Management process includes bottom-up estimating as a tool or technique?

Options:

A.

Estimate Activity Resources


B.

Sequence Activities


C.

Estimate Activity Durations


D.

Develop Schedule


Expert Solution
Questions # 70:

Which output is the approved version of the time-phased project budget?

Options:

A.

Resource calendar


B.

Scope baseline


C.

Trend analysis


D.

Cost baseline


Expert Solution
Questions # 71:

A risk that arises as a direct result of implementing a risk response is called a:

Options:

A.

contingent risk


B.

residual risk


C.

potential risk


D.

secondary risk


Expert Solution
Questions # 72:

Tools and techniques used in Direct and Manage Project Work include:

Options:

A.

Process analysis and expert judgment


B.

Analytical techniques and a project management information system


C.

Performance reviews and meetings


D.

Expert judgment and meetings


Expert Solution
Questions # 73:

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Options:

A.

Information management systems


B.

Work performance reports


C.

Stakeholder analysis


D.

Data gathering and representation


Expert Solution
Questions # 74:

Variance and trend analysis is a tool and technique used in which process?

Options:

A.

Perform Qualitative Risk Analysis


B.

Perform Quantitative Risk Analysis


C.

Control Risks


D.

Plan Risk Responses


Expert Solution
Questions # 75:

The following is a network diagram for a project.

Question # 75

The critical path for the project is how many days in duration?

Options:

A.

10


B.

12


C.

14


D.

17


Expert Solution
Questions # 76:

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

Options:

A.

organizational skills


B.

technical skills


C.

communication skills


D.

hard skills


Expert Solution
Questions # 77:

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

Options:

A.

risk management plan


B.

human resource management plan


C.

scope management plan


D.

procurement management plan


Expert Solution
Questions # 78:

Analytical techniques are a tool and technique of which process in Project Procurement Management?

Options:

A.

Plan Procurement Management


B.

Control Procurements


C.

Conduct Procurements


D.

Close Procurements


Expert Solution
Questions # 79:

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

Options:

A.

Forecasting,


B.

Brainstorming.


C.

Historical databases.


D.

Cost of quality.


Expert Solution
Questions # 80:

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?

Options:

A.

The development team ran out of time and did not pull the social media story from the backlog.


B.

The development team completed all of the stories identified by the product owner as having the highest customer value.


C.

The sprint demo went smoothly and the team did not find any open issues.


D.

The social media story is a marketing priority and less important than other priorities.


Expert Solution
Questions # 81:

Which process determines the correctness of deliverables?

Options:

A.

Verify Deliverables


B.

Validate Deliverables


C.

Review Deliverables


D.

Analyze Deliverables


Expert Solution
Questions # 82:

Who defines the scope of the product

Options:

A.

The client


B.

The project manager


C.

The team


D.

The program manager


Expert Solution
Questions # 83:

A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?

Options:

A.

-12


B.

1.15


C.

38


D.

12


Expert Solution
Questions # 84:

During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?

Options:

A.

Asked the stakeholders to write the requirements themselves


B.

Included the project manager in the elicitation sessions


C.

Confirmed the elicitation results after sessions


D.

Updated the requirements traceability matrix


Expert Solution
Questions # 85:

A project manager needs to determine the schedule variance (SV). The project manager's latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?

Options:

A.

-9


B.

37


C.

9


D.

322


Expert Solution
Questions # 86:

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

Options:

A.

Defining, sequencing, estimating activity duration, and developing a schedule model are so tightly inked that they are viewed as a single process.


B.

The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge


C.

An iterative scheduling and on-demand, pull-based scheduling will be required.


D.

To address the full delivery schedule, a range of techniques may be needed and then need to be adapted


Expert Solution
Questions # 87:

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

Options:

A.

-700


B.

-200


C.

200


D.

500


Expert Solution
Questions # 88:

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

Options:

A.

Organizational standard processes


B.

Marketplace conditions


C.

Historical information


D.

Templates


Expert Solution
Questions # 89:

Taking out insurance in relation to risk management is called what?

Options:

A.

Transference


B.

Avoidance


C.

Exploring


D.

Mitigation


Expert Solution
Questions # 90:

Projects are undertaken by an organization to support the:

Options:

A.

Product performance.


B.

Budget process.


C.

Collective capabilities.


D.

Organizational strategy.


Expert Solution
Questions # 91:

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One


B.

Five


C.

Six


D.

Seven


Expert Solution
Questions # 92:

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.


B.

establishes project roles and responsibilities.


C.

improves teamwork, interpersonal skills, and competencies.


D.

provides an accurate appraisal of team member performance.


Expert Solution
Questions # 93:

Success is measured by benefits realization for a:

Options:

A.

strategic plan


B.

project


C.

portfolio


D.

program


Expert Solution
Questions # 94:

At the start of a typical project life cycle, costs are:

Options:

A.

low, peak as work is carried out, and drop as the project nears the end.


B.

low, become steady as work is carried out, and increase as the project nears the end.


C.

high, drop as work is carried out, and increase as the project nears the end.


D.

high, become low as work is carried out, and drop as the project nears the end.


Expert Solution
Questions # 95:

For a stakeholder with low interest and high power, the project manager should:

Options:

A.

Monitor the stakeholder.


B.

Manage the stakeholder closely.


C.

Keep the stakeholder satisfied.


D.

Keep the stakeholder informed.


Expert Solution
Questions # 96:

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.


B.

A stakeholder management plan.


C.

Project team building.


D.

Integrated change control.


Expert Solution
Questions # 97:

The following is a network diagram for a project.

Question # 97

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I


B.

A-B-C-F-H-I


C.

A-D-E-F-G-I


D.

A-D-E-F-H-I


Expert Solution
Questions # 98:

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

Options:

A.

Analysis


B.

Appetite


C.

Tolerance


D.

Response


Expert Solution
Questions # 99:

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

Options:

A.

Communication models.


B.

Stakeholder participation.


C.

Expert judgment


D.

Enterprise environmental factors.


Expert Solution
Questions # 100:

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal


B.

External


C.

Discretionary


D.

Mandatory


Expert Solution
Viewing page 2 out of 8 pages
Viewing questions 51-100 out of questions