Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 2 out of 8 pages
Viewing questions 51-100 out of questions
Questions # 51:

An input to the Estimate Activity Resources process is:

Options:

A.

Activity resource requirements.


B.

Published estimating data.


C.

Resource calendars.


D.

Resource breakdown structure (RBS).


Expert Solution
Questions # 52:

Which is an output of the Collect Requirements process?

Options:

A.

Requirements traceability matrix


B.

Project scope statement


C.

WBS dictionary


D.

Work performance measurements


Expert Solution
Questions # 53:

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode


B.

Encode


C.

Medium


D.

Noise


Expert Solution
Questions # 54:

What happens to a stakeholder's project influence over time?

Options:

A.

Increases


B.

Decreases


C.

Stays the same


D.

Has no bearing


Expert Solution
Questions # 55:

Which baselines make up the performance measurement baseline?

Options:

A.

Scope baseline, cost baseline, and schedule baseline


B.

Scope baseline, project management baseline, and quality baseline


C.

Cost baseline, schedule baseline, and risk baseline


D.

Cost baseline, project management baseline, and schedule baseline


Expert Solution
Questions # 56:

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.


B.

complete project work.


C.

calculate costs.


D.

Develop Project Management Plan.


Expert Solution
Questions # 57:

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager


B.

Constantly evolving


C.

The sum of all knowledge related to project management


D.

A sum of knowledge that should be applied on every project


Expert Solution
Questions # 58:

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate


B.

Transfer


C.

Exploit


D.

Avoid


Expert Solution
Questions # 59:

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs


B.

Determine Budget


C.

Estimate Costs


D.

Control Budget


Expert Solution
Questions # 60:

Risk exists the moment that a project is:

Options:

A.

planned.


B.

conceived.


C.

chartered.


D.

executed.


Expert Solution
Questions # 61:

The staffing management plan is part of the:

Options:

A.

organizational process assets.


B.

resource calendar.


C.

human resource plan.


D.

Develop Project Team process.


Expert Solution
Questions # 62:

At the end of the project, what will be the value of SV?

Options:

A.

Positive


B.

Zero


C.

Negative


D.

Greater than one


Expert Solution
Questions # 63:

Who is responsible for initiating a project?

Options:

A.

Project sponsor


B.

Project manager


C.

Program manager


D.

Project management office (PMO)


Expert Solution
Questions # 64:

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Options:

A.

operate separately.


B.

move together in batches,


C.

overlap and interact.


D.

move in a sequence.


Expert Solution
Questions # 65:

Which of the following is a project constraint?

Options:

A.

Twenty-five percent staff turnover is expected.


B.

The technology to be used is cutting-edge.


C.

Project leadership may change due to volatile political environment.


D.

The product is needed in 250 days.


Expert Solution
Questions # 66:

The risk shared between the buyer and seller is determined by the:

Options:

A.

assumption log.


B.

quality checklist.


C.

risk register.


D.

contract type.


Expert Solution
Questions # 67:

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.


B.

statistical sampling.


C.

management responsibility,


D.

continuous improvement.


Expert Solution
Questions # 68:

Which process requires implementation of approved changes?

Options:

A.

Direct and Manage Project Execution


B.

Monitor and Control Project Work


C.

Perform Integrated Change Control


D.

Close Project or Phase


Expert Solution
Questions # 69:

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence


B.

Value of each possible outcome multiplied by probability of non-occurrence


C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together


D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together


Expert Solution
Questions # 70:

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied


B.

Keep informed


C.

Manage closely


D.

Monitor


Expert Solution
Questions # 71:

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:

A.

event.


B.

response,


C.

perception.


D.

impact.


Expert Solution
Questions # 72:

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating


B.

Planning


C.

Executing


D.

Monitoring and Controlling


Expert Solution
Questions # 73:

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).


B.

schedule target.


C.

performance measurement baseline (PMB).


D.

earned value baseline.


Expert Solution
Questions # 74:

Risk responses reflect an organization's perceived balance between:

Options:

A.

risk taking and risk avoidance.


B.

known risk and unknown risk.


C.

identified risk and analyzed risk.


D.

varying degrees of risk.


Expert Solution
Questions # 75:

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.


B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.


C.

a recognized standard for the project management profession.


D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.


Expert Solution
Questions # 76:

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

Options:

A.

Project


B.

Scope


C.

Contract


D.

Program


Expert Solution
Questions # 77:

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Performance reports


B.

Project charter


C.

Outputs from planning processes


D.

Enterprise environmental factors


Expert Solution
Questions # 78:

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

Options:

A.

Sensitivity analysis


B.

Three-point estimate


C.

Modeling and simulation


D.

Expected monetary value analysis


Expert Solution
Questions # 79:

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment


B.

Risk registry


C.

Risk response planning


D.

Interviewing


Expert Solution
Questions # 80:

Which Process Group contains those processes performed to define a new project?

Options:

A.

Initiating


B.

Planning


C.

Executing


D.

Closing


Expert Solution
Questions # 81:

The definition of operations is a/an:

Options:

A.

organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.


B.

temporary endeavor undertaken to create a unique product, service, or result.


C.

organization that provides oversight for an administrative area.


D.

organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.


Expert Solution
Questions # 82:

What is the responsibility of the project manager and the functional manager respectively?

Options:

A.

Oversight for an administrative area; a facet of the core business


B.

Achieving the project objectives; providing management oversight for an administrative area


C.

A facet of the core business; achieving the project objectives


D.

Both are responsible for achieving the project objectives.


Expert Solution
Questions # 83:

A weighting system is a tool for which area of Conduct Procurements?

Options:

A.

Plan contracting


B.

Requesting seller responses


C.

Selecting seller's


D.

Planning purchase and acquisition


Expert Solution
Questions # 84:

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

Options:

A.

Exploit


B.

Share


C.

Enhance


D.

Transfer


Expert Solution
Questions # 85:

Which type of estimating is used to improve the accuracy of an activity's duration?

Options:

A.

Analogous


B.

Parametric


C.

Three-point


D.

What-if scenario analysis


Expert Solution
Questions # 86:

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

Options:

A.

Authority


B.

Role


C.

Competency


D.

Responsibility


Expert Solution
Questions # 87:

Documented identification of a flaw in a project component together with a recommendation is termed a:

Options:

A.

corrective action.


B.

preventive action.


C.

non-conformance report,


D.

defect repair.


Expert Solution
Questions # 88:

Which is an output from Distribute Information?

Options:

A.

Earned value analysis


B.

Trend analysis


C.

Project records


D.

Performance reviews


Expert Solution
Questions # 89:

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory


B.

Activity list


C.

WBS


D.

Project schedule


Expert Solution
Questions # 90:

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Cost-benefit analysis


B.

Updated project charter


C.

Approved change request


D.

Multicriteria decision analysis


Expert Solution
Questions # 91:

When sequencing activities, what does the common acronym FF stand for?

Options:

A.

Fixed Fee


B.

Free Float


C.

Fixed Finish


D.

Finish-to-Finish


Expert Solution
Questions # 92:

Which of the following is an example of schedule compression?

Options:

A.

Activity sequencing


B.

Resource leveling


C.

Lead and lag adjusting


D.

Crashing


Expert Solution
Questions # 93:

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities


B.

Estimate Activity Durations


C.

Estimate Activity Resources


D.

Sequence Activities


Expert Solution
Questions # 94:

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide


B.

The Standard for Program Management


C.

Organizational Project Management Maturity Model (OPM3$)


D.

Guide to the Project Management Body of Knowledge (PMBOKĀ®)


Expert Solution
Questions # 95:

Which characteristic do projects and operational work share in common?

Options:

A.

Performed by systems


B.

Constrained by limited resources


C.

Repetitiveness


D.

Uniqueness


Expert Solution
Questions # 96:

In which Process Group are lessons learned documented?

Options:

A.

Planning


B.

Closing


C.

Executing


D.

Initiating


Expert Solution
Questions # 97:

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

Options:

A.

Determine Budget.


B.

Baseline Budget.


C.

Control Costs.


D.

Estimate Costs.


Expert Solution
Questions # 98:

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

Options:

A.

Plan Risk Responses


B.

Manage Stakeholder Expectations


C.

Define Scope


D.

Report Performance


Expert Solution
Questions # 99:

Change request status updates are an output of which process?

Options:

A.

Perform Integrated Change Control


B.

Direct and Manage Project Execution


C.

Close Project or Phase


D.

Monitor and Control Project Work


Expert Solution
Questions # 100:

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

Options:

A.

Planning


B.

Executing


C.

Closing


D.

Initiating


Expert Solution
Viewing page 2 out of 8 pages
Viewing questions 51-100 out of questions