The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
An input to the Perform Integrated Change Control process is:
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
The following is a network diagram for a project.

The free float for Activity H is how many days?
The component of the risk management plan that documents how risk activities will be recorded is called:
The primary benefit of the Plan Schedule Management process is that it:
A project manager who communicates to the project team though email is using which type of communication?
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
High-level project risks are included in which document?
When closing a project or phase, part of the process may require the use of which type of analysis?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
An input to the Control Quality process is:
Which items are components of a project management plan?
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
A graphic display of project team members and their reporting relationships is known as a:
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
Which Project Time Management process includes bottom-up estimating as a tool or technique?
Which output is the approved version of the time-phased project budget?
A risk that arises as a direct result of implementing a risk response is called a:
Tools and techniques used in Direct and Manage Project Work include:
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
Variance and trend analysis is a tool and technique used in which process?
The following is a network diagram for a project.

The critical path for the project is how many days in duration?
Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
Analytical techniques are a tool and technique of which process in Project Procurement Management?
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.
Why was the product still determined to be ready for delivery?
Which process determines the correctness of deliverables?
Who defines the scope of the product
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?
A project manager needs to determine the schedule variance (SV). The project manager's latest schedule indicates 14 units of work completed against a plan of 23 units.
What is the SV?
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?
Taking out insurance in relation to risk management is called what?
Projects are undertaken by an organization to support the:
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
One of the key benefits of the Plan Human Resource Management process is that it:
Success is measured by benefits realization for a:
At the start of a typical project life cycle, costs are:
For a stakeholder with low interest and high power, the project manager should:
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:
The following is a network diagram for a project.

What is the critical path for the project?
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?