A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?


A.

Provide the information to the product manager for approval.


B.

Provide the information to the project manager to seek approval or rejection.


C.

Reject the change as the project scope has already been defined.


D.

Accept the modification and update the requirements traceability matrix.