CAPM Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost


A.

High-level deliverables


B.

Success criteria


C.

Project objectives


D.

Phase transitions