PMI Certified Associate in Project Management (CAPM) CAPM Question # 66 Topic 7 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 66 Topic 7 Discussion

CAPM Exam Topic 7 Question 66 Discussion:
Question #: 66
Topic #: 7

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?


A.

Use a lightweight cost estimation due to the nature of angile projects.


B.

Use a detailed cost estimation for agile projects.


C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.


D.

Use a detailed work breakdown structure (WBS) to get cost estimation.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.