New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 66 Topic 7 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 66 Topic 7 Discussion

CAPM Exam Topic 7 Question 66 Discussion:
Question #: 66
Topic #: 7

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?


A.

Plan Stakeholder Management


B.

Identify Stakeholders


C.

Manage Stakeholder Engagement


D.

Control Stakeholder Engagement


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.