PMI Certified Associate in Project Management (CAPM) CAPM Question # 84 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 84 Topic 9 Discussion

CAPM Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

A project manager needs to request outside support......manager need to create

A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?


A.

Time and material (T&M)


B.

Cost plus fixed fee (CPFF)


C.

Fixed price


D.

Cost plus award fee (CPAF)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.