New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 84 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 84 Topic 9 Discussion

CAPM Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?


A.

Asked the stakeholders to write the requirements themselves


B.

Included the project manager in the elicitation sessions


C.

Confirmed the elicitation results after sessions


D.

Updated the requirements traceability matrix


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.