Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 84 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 84 Topic 9 Discussion

CAPM Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?


A.

Analogous


B.

Parametric


C.

Bottom-up


D.

Top-down


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.