Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 61 Topic 7 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 61 Topic 7 Discussion

CAPM Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3


A.

5


B.

2


C.

3


D.

4


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.