PMI Certified Associate in Project Management (CAPM) CAPM Question # 372 Topic 38 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 372 Topic 38 Discussion

CAPM Exam Topic 38 Question 372 Discussion:
Question #: 372
Topic #: 38

Which of the following processes are part of the Project Integration Management Knowledge Area?


A.

Develop Project Management Plan, Collect Requirements, Create WBS


B.

Develop Project Management Plan, Control Scope, Develop Schedule


C.

Develop Project Charter, Define Scope, Estimate Costs


D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.