New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 371 Topic 38 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 371 Topic 38 Discussion

CAPM Exam Topic 38 Question 371 Discussion:
Question #: 371
Topic #: 38

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?


A.

Escalate this issue to the project management office (PMO).


B.

Escalate this issue to the chief financial officer (CFO).


C.

Escalate this issue to the procurement team.


D.

Escalate this issue to the project sponsor.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.