A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?


A.

A diagram in which resource optimization has been applied.


B.

A diagram in which the critical path method has been applied.


C.

A diagram in which a predefined series of activities has been organized.


D.

A diagram which shows a combination of resource and time optimization.