Question #: 8
Topic #: 1

Which contract type is least desirable to a vendor?


A.

Fixed price with economic price adjustment (FPEPA)


B.

Firm fixed price (FFP)


C.

Cost plus fixed fee (CPFF>


D.

Cost plus award fee (CPAF>