Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 90 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 90 Topic 10 Discussion

CAPM Exam Topic 10 Question 90 Discussion:
Question #: 90
Topic #: 10

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?


A.

Transfer


B.

Share


C.

Avoid


D.

Accept


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.