Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 91 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 91 Topic 10 Discussion

CAPM Exam Topic 10 Question 91 Discussion:
Question #: 91
Topic #: 10

A project lead asks the team to create a work breakdown structure (WBS) of the project's scope. The team is confused about how far they should break down the scope.

What should the project lead tell the team?


A.

Decompose to the activity or task level.


B.

Decompose until all of the risks are identified.


C.

Decompose to the work package level.


D.

Decompose until a WBS dictionary is obtained.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.