Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 91 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 91 Topic 10 Discussion

CAPM Exam Topic 10 Question 91 Discussion:
Question #: 91
Topic #: 10

A stakeholder asked the project manager to add an additional feature to the project scope. The project manager is unsure whether the project budget will allow this additional scope.

What component of the project management plan should the project manager reference to determine whether the budget will allow a new feature to be added?


A.

Risk management plan


B.

Cost estimate


C.

Risk register


D.

Cost management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.