PMI Certified Associate in Project Management (CAPM) CAPM Question # 89 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 89 Topic 9 Discussion

CAPM Exam Topic 9 Question 89 Discussion:
Question #: 89
Topic #: 9

A project manager needs to determine the schedule variance (SV). The project manager's latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?


A.

-9


B.

37


C.

9


D.

322


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.