PMI Certified Associate in Project Management (CAPM) CAPM Question # 80 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 80 Topic 9 Discussion

CAPM Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?


A.

USS-30,000


B.

US$120,000


C.

US$370,000


D.

US$400,000