New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 80 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 80 Topic 9 Discussion

CAPM Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?


A.

The development team ran out of time and did not pull the social media story from the backlog.


B.

The development team completed all of the stories identified by the product owner as having the highest customer value.


C.

The sprint demo went smoothly and the team did not find any open issues.


D.

The social media story is a marketing priority and less important than other priorities.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.