PMI Certified Associate in Project Management (CAPM) CAPM Question # 79 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 79 Topic 8 Discussion

CAPM Exam Topic 8 Question 79 Discussion:
Question #: 79
Topic #: 8

A project team member identifies a possibility......the team member's idea?

A project team member identifies a possibility of increasing project performance by adopting an innovative approach to a proposed solution. This also will save resources for the company and increase stakeholder satisfaction.

How should the project manager evaluate the team member's idea?


A.

Treat the idea using risk management processes, to handle it in a controlled and managed way.


B.

Perform an experiment simulation to confirm idea results, to make sure the cost to implement is worthwhile.


C.

Do a feasibility analysis study to confirm if an investment to explore a solution will add value.


D.

Submit the idea as a change request to the change control board to ensure that all interests are met.