New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 30 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 30 Topic 4 Discussion

CAPM Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

Scope, schedule, and cost parameters are integrated in the:


A.

Performance measurement baseline.


B.

Analysis of project forecasts,


C.

Summary of changes approved in a period,


D.

Analysis of past performance.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.