PMI Certified Associate in Project Management (CAPM) CAPM Question # 170 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 170 Topic 18 Discussion

CAPM Exam Topic 18 Question 170 Discussion:
Question #: 170
Topic #: 18

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?


A.

Coaching


B.

Avoidance


C.

Consensus


D.

Influencing


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.