A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?
A.
Earned value (EV) / actual cost (AC)
B.
Estimate at completion (EAC) - AC
C.
Budget at completion (BAC) / cost performance index (CPI)