Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 170 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 170 Topic 18 Discussion

CAPM Exam Topic 18 Question 170 Discussion:
Question #: 170
Topic #: 18

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?


A.

100


B.

120


C.

1,000


D.

1,200


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.