New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 171 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 171 Topic 18 Discussion

CAPM Exam Topic 18 Question 171 Discussion:
Question #: 171
Topic #: 18

On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.

What is the advantage of using this tool?


A.

Scope creep will be prevented.


B.

Resource allocation will be kept to a minimum.


C.

Project closure will be established.


D.

Project costs will be controlled.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.