PMI Certified Associate in Project Management (CAPM) CAPM Question # 171 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 171 Topic 18 Discussion

CAPM Exam Topic 18 Question 171 Discussion:
Question #: 171
Topic #: 18

At which point of the project is the uncertainty the highest and the risk of failing the greatest?


A.

Final phase of the project


B.

Start of the project


C.

End of the project


D.

Midpoint of the project


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.