PMI Certified Associate in Project Management (CAPM) CAPM Question # 56 Topic 6 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 56 Topic 6 Discussion

CAPM Exam Topic 6 Question 56 Discussion:
Question #: 56
Topic #: 6

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:


A.

Control Schedule.


B.

Quality Control.


C.

Perform Integrated Change Control.


D.

Develop Schedule.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.