Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 82 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 82 Topic 9 Discussion

CAPM Exam Topic 9 Question 82 Discussion:
Question #: 82
Topic #: 9

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?


A.

Discuss the processes and deliverables needed to meet the project objectives with the team.


B.

Integrate hybrid approach processes and deliverables to meet the short delivery time line.


C.

Identify the processes and deliverables for only the current phase first.


D.

Follow organizational methodology and produce all required deliverables.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.