PMI Certified Associate in Project Management (CAPM) CAPM Question # 82 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 82 Topic 9 Discussion

CAPM Exam Topic 9 Question 82 Discussion:
Question #: 82
Topic #: 9

A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity's prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

How should the project manager proceed?


A.

Perform Integrated Change Control.


B.

Conduct a risk assessment with the team.


C.

Update the schedule to include compliance.


D.

Manage Stakeholder Engagement.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.