A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
A.
Discuss the processes and deliverables needed to meet the project objectives with the team.
B.
Integrate hybrid approach processes and deliverables to meet the short delivery time line.
C.
Identify the processes and deliverables for only the current phase first.
D.
Follow organizational methodology and produce all required deliverables.
In the PMBOK® Guide, the act of deciding which processes are appropriate for a specific project is known as Tailoring. Even in a Predictive approach, the project manager does not blindly follow every possible process; instead, they select the most relevant tools and techniques based on the project’s unique context.
Why Choice A is correct:
Collaboration: The Project Manager (PM) should not work in a vacuum. Engaging the project team allows the PM to leverage the specialized expertise of team members to identify which processes are necessary to create the specific deliverables required.
Value-Driven: By focusing on the " project objectives, " the team ensures that every process included in the management plan adds value and contributes to the final goal, rather than just adding administrative overhead.
Buy-in: Involving the team early in the planning process (specifically during the Develop Project Management Plan process) fosters a sense of ownership and clarity regarding their roles and responsibilities.
Analysis of other options:
B (Integrate hybrid approach): The question specifically states this is a " predictive approach. " Forcing a hybrid model solely due to a six-month timeline is a change in strategy that may not be appropriate if the scope is stable and well-defined.
C (Identify processes for only current phase): While this describes Rolling Wave Planning, the question asks about determining the processes for the Project Management Plan (the master document). A PM plan must define the overall methodology for the entire project lifecycle, even if certain details are elaborated later.
D (Follow organizational methodology for all deliverables): This is " rigid " project management. Organizations provide a methodology as a framework, but PMI emphasizes that the PM must still tailor that framework. Producing " all " deliverables without considering necessity leads to waste.
Tailoring Considerations: The PM and the team should consider the project’s size, complexity, and regulatory environment. For a six-month project, " Lean " predictive management might be preferred over a heavy, documentation-intensive process. Choice A ensures the resulting plan is " fit for purpose. "