PMI Certified Associate in Project Management (CAPM) CAPM Question # 82 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 82 Topic 9 Discussion

CAPM Exam Topic 9 Question 82 Discussion:
Question #: 82
Topic #: 9

What is the responsibility of the project manager and the functional manager respectively?


A.

Oversight for an administrative area; a facet of the core business


B.

Achieving the project objectives; providing management oversight for an administrative area


C.

A facet of the core business; achieving the project objectives


D.

Both are responsible for achieving the project objectives.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.