New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 86 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 86 Topic 9 Discussion

CAPM Exam Topic 9 Question 86 Discussion:
Question #: 86
Topic #: 9

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?


A.

Defining, sequencing, estimating activity duration, and developing a schedule model are so tightly inked that they are viewed as a single process.


B.

The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge


C.

An iterative scheduling and on-demand, pull-based scheduling will be required.


D.

To address the full delivery schedule, a range of techniques may be needed and then need to be adapted


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.