Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 139 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 139 Topic 14 Discussion

CAPM Exam Topic 14 Question 139 Discussion:
Question #: 139
Topic #: 14

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?


A.

8


B.

18


C.

36


D.

40


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.