PMI Certified Associate in Project Management (CAPM) CAPM Question # 139 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 139 Topic 14 Discussion

CAPM Exam Topic 14 Question 139 Discussion:
Question #: 139
Topic #: 14

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?


A.

Change request


B.

Risk response


C.

Risk management plan


D.

Lessons learned


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.