CAPM Exam Topic 10 Question 94 Discussion:
Question #: 94
Topic #: 10

Which schedule network analysis technique modifies the project schedule to account for limited resources?


A.

Human resource planning


B.

Fast tracking


C.

Critical chain method


D.

Rolling wave planning