Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 7 out of 8 pages
Viewing questions 301-350 out of questions
Questions # 301:

An output of the Plan Quality Management process is:

Options:

A.

A process improvement plan,


B.

Quality control measurements.


C.

Work performance information,


D.

The project management plan.


Expert Solution
Questions # 302:

An output of the Direct and Manage Project Work process is:

Options:

A.

Deliverables.


B.

Activity lists.


C.

A work breakdown structure.


D.

A scope statement.


Expert Solution
Questions # 303:

An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

Options:

A.

smooth/accommodate.


B.

force/direct,


C.

collaborate/problem solve,


D.

compromise/reconcile.


Expert Solution
Questions # 304:

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan


B.

Project charter


C.

Project management plan


D.

Service level agreement


Expert Solution
Questions # 305:

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Options:

A.

Scope baseline


B.

Organizational process assets


C.

Enterprise environmental factors


D.

Risk register


Expert Solution
Questions # 306:

The process of prioritizing risks for further analysis or action is known as:

Options:

A.

Plan Risk Management.


B.

Plan Risk Responses.


C.

Perform Qualitative Risk Analysis.


D.

Perform Quantitative Risk Analysis.


Expert Solution
Questions # 307:

In which Knowledge Area is the project charter developed?

Options:

A.

Project Cost Management


B.

Project Scope Management


C.

Project Time Management


D.

Project Integration Management


Expert Solution
Questions # 308:

An input to Develop Project Charter is a/an:

Options:

A.

Business case.


B.

Activity list.


C.

Project management plan.


D.

Cost forecast.


Expert Solution
Questions # 309:

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment


B.

Forecasting methods


C.

Earned value management


D.

Analytical techniques


Expert Solution
Questions # 310:

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.


B.

Risk and uncertainty increase; the cost of changes decreases,


C.

Risk and uncertainty decrease; the cost of changes increases.


D.

Risk and uncertainty decrease; the cost of changes decreases.


Expert Solution
Questions # 311:

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

Options:

A.

Earned value management.


B.

Enterprise environmental factors.


C.

Organizational process assets.


D.

Work performance information.


Expert Solution
Questions # 312:

The Identify Stakeholders process is found in which Process Group?

Options:

A.

Initiating


B.

Monitoring and Controlling


C.

Planning


D.

Executing


Expert Solution
Questions # 313:

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

Options:

A.

Add the milestones to the risk register, as time is short.


B.

Add the two milestones to the project plan, as they are mandatory.


C.

Calculate the duration of the two milestones stated in the contract.


D.

Start the project as soon as possible, as time is short.


Expert Solution
Questions # 314:

An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?

Options:

A.

Risk register


B.

Sprint board


C.

Sprint planning


D.

User story


Expert Solution
Questions # 315:

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?

Options:

A.

Strategic and business management skills


B.

Leadership skills


C.

Technical project management


D.

Organizational management


Expert Solution
Questions # 316:

What is the main purpose of Project Quality Management?

Options:

A.

To meet customer requirements by overworking the team


B.

To fulfill project schedule objectives by rushing planned inspections


C.

To fulfill project requirements of both quality and grade


D.

To exceed customer expectations


Expert Solution
Questions # 317:

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

Options:

A.

Portfolios


B.

Standards


C.

Concepts


D.

Programs


Expert Solution
Questions # 318:

A software development team is working on a project to adapt an application to new, government-established data-privacy rules. What factor led to the creation of this project?

Options:

A.

Legal requirement


B.

New technology


C.

Social need


D.

Economic change


Expert Solution
Questions # 319:

What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?

Options:

A.

Get expert judgment.


B.

Count on personal experience.


C.

Ask project sponsors.


D.

Delay the project until technical uncertainty is clarified


Expert Solution
Questions # 320:

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

Options:

A.

Risk burnup and control chart


B.

Customer satisfaction index and workload


C.

Average burndown and velocity


D.

Average velocity and cycle time


Expert Solution
Questions # 321:

Which is a method of prototyping that creates a functioning representation of the final finished product to the user?

Options:

A.

Low-fidelity prototyping


B.

High-fidelity prototyping


C.

Data prototyping


D.

Report prototyping


Expert Solution
Questions # 322:

A project manager is assigned to a project during the execution phase and consults the documents created by the previous project manager.

Which document should the project manager study to identify the ownership of the project outcome?

Options:

A.

The lessons learned repository


B.

The project charter


C.

The business case


D.

The organizational plan


Expert Solution
Questions # 323:

A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone.

To reduce the risk with this approach, which step should the business analyst take?

Options:

A.

Add the risk to the risk register so other stakeholders are aware of the approach.


B.

Distribute the documented requirements to relevant stakeholders in all time zones for review and comment.


C.

Ask the stakeholders in the elicitation sessions to speak on behalf of stakeholders in other time zones.


D.

Request the project sponsor to approve this requirements elicitation approach for this project.


Expert Solution
Questions # 324:

Among all of the key stakeholders in an agile project, who is responsible for creating project requirements for the team?

Options:

A.

Scrum master


B.

Project manager


C.

Business analyst


D.

Project management office


Expert Solution
Questions # 325:

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

Options:

A.

Resource availability


B.

Infrastructure


C.

Academic research


D.

Corporate knowledge base


Expert Solution
Questions # 326:

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

Options:

A.

-8


B.

425


C.

1.4


D.

8


Expert Solution
Questions # 327:

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

Options:

A.

Static payback period = 6 + 1300 / 500 = 6.6


B.

Static payback period = 3 + 1200 / 500 = 5.4


C.

Static payback period = 5 + 700 / 500 = 5.4


D.

Static payback period = 5 + 200 / 500 = 5.4


Expert Solution
Questions # 328:

While working in an adaptive environment, a business analyst is collaborating with other roles in drafting a product roadmap. Which three roles are involved in establishing the product roadmap? (Choose three)

Options:

A.

Project sponsor


B.

Portfolio manager


C.

End user


D.

Program manager


E.

Internal inspector


Expert Solution
Questions # 329:

What can a requirements traceability matrix enable regardless of the project methodology being used?

Options:

A.

Creation of a solid business case


B.

Investigation of the viability of a new product


C.

Identification of missing and superfluous requirements


D.

Evaluation of solution and system performance


Expert Solution
Questions # 330:

Which of these is a hybrid contract?

Options:

A.

Cost plus award fee (CPAF)


B.

Firm fixed price (FFP)


C.

Fixed price incentive fee (FPIF)


D.

Time and material (T&M)


Expert Solution
Questions # 331:

Which of the following set of items belongs to the communications management plan?

Options:

A.

Escalation processes and meeting management


B.

Project schedule and glossary of common terminology


C.

Escalation processes and stakeholder communication requirements


D.

Interactive communication model and information to be communicated


Expert Solution
Questions # 332:

Match the process with its corresponding process group.


Expert Solution
Questions # 333:

Which of these statements is true of subsidiary management plans?

Options:

A.

Subsidiary management plans are mandatory for any project


B.

Subsidiary management plans use the project charier as input


C.

Subsidiary management plans can be independently managed


D.

Subsidiary management plans do not need regular updates


Expert Solution
Questions # 334:

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?

Options:

A.

Develop consensus among stakeholders


B.

Get the budget approved for change


C.

Make sure management is aware of the change


D.

Get approval from the change control board


Expert Solution
Questions # 335:

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

Options:

A.

Escalate this issue to the project management office (PMO).


B.

Escalate this issue to the chief financial officer (CFO).


C.

Escalate this issue to the procurement team.


D.

Escalate this issue to the project sponsor.


Expert Solution
Questions # 336:

A business analyst sent multiple meeting requests via instant message to a subject matter expert (SME) working in another country but did not receive a response. What should the business analyst do to reduce the likelihood of this occurring in the future with other stakeholders distributed across multiple locations?

Options:

A.

Ask each stakeholder for their preferred communication method.


B.

Confirm the time zone and work days in each location.


C.

Check with the IT department to see if there is a technical issue.


D.

Assume the meeting request is accepted unless declined.


Expert Solution
Questions # 337:

A Project manager is using agile in a project. As development life cycle is adaptive, how does the project manager handle key stakeholder involvement?

Options:

A.

Key stakeholders are regularly involved


B.

Key stakeholders are continuously involved


C.

Key stakeholders are involved at specific milestones


D.

Key stakeholders are always involved


Expert Solution
Questions # 338:

A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?

Options:

A.

Forward the status reports to the stakeholder.


B.

Manage stakeholder engagement.


C.

Consult the communications management plan.


D.

Update the communications management plan.


Expert Solution
Questions # 339:

To ensure stakeholder satisfaction; identified stakeholder needs should all be

Options:

A.

Vetted


B.

Ranked from greatest to least


C.

Qualified


D.

Documented in the stakeholder engagement plan


Expert Solution
Questions # 340:

Match each Project Cost Management process with its appropriate keyword


Expert Solution
Questions # 341:

Which of the following projects is a quality candidate for adaptive approaches?

Options:

A.

Installing new computers across offices


B.

Retrofitting an old building


C.

Upgrading an information system


D.

Designing a new suspension bridge


Expert Solution
Questions # 342:

A Scrum team has a product backlog and a sprint backlog. Which of the following is a correct statement related to these artifacts?

Options:

A.

The product backlog does not contain a prioritized list of requirements.


B.

The sprint backlog contains items to be completed during the current sprint.


C.

The sprint backlog contains the list of items prioritized by the product owner.


D.

The product backlog is a subset of the sprint backlog.


Expert Solution
Questions # 343:

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

Options:

A.

Three-point


B.

Bottom-up


C.

Parametric


D.

Analogous


Expert Solution
Questions # 344:

Which three techniques can be estimate costs?

Options:

A.

Financing, bottom-up estimating, and expert judgment


B.

Cost aggregation, analogous estimating, and financing


C.

Expert judgment, financing, and cost aggregation


D.

Expert judgment, analogous estimating, and bottom-up estimating


Expert Solution
Questions # 345:

The activity tailoring is necessary because:

Options:

A.

the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects


B.

each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide


C.

the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects


D.

each project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide


Expert Solution
Questions # 346:

A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?

Options:

A.

Review the project management plan.


B.

Share the requirements traceability matrix the same way it was shared previously.


C.

Consult the business analysis communications management plan.


D.

Ask the project manager to share the updated requirements traceability matrix at the next meeting.


Expert Solution
Questions # 347:

Which of the following is an input to the Perform Qualitative Risk Analysis process?

Options:

A.

Risk register


B.

Risk data quality assessment


C.

Risk categorization


D.

Risk urgency


Expert Solution
Questions # 348:

During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.

What should the project manager do?

Options:

A.

Inform the stakeholders that the stakeholder register needs to be recreated, as the team does not understand the requirements.


B.

Share the project management plan with the team members again to bring them up to speed on the requirements.


C.

Schedule additional meetings with the customer to explain the requirements for each deliverable at length.


D.

Revisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.


Expert Solution
Questions # 349:

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment


B.

Risk registry


C.

Risk response planning


D.

Interviewing


Expert Solution
Questions # 350:

A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month each. This will help this small enterprise to have a return on investment (ROI) as the project runs from the first cycle. Which methodology should the project manager adopt and implement in the project?

Options:

A.

Feature-driven development (FDD) as it will deliver product segments and the milestones are controlled by the development manager.


B.

Kanban as it will provide flexibility to the team for working at their own pace in the time frame requested.


C.

Scrum as it uses sprints and retrospectives, maximizing time delivery and the value of the product.


D.

Extreme Programming (XP) as it will help deliver more quickly since developers will work in pairs.


Expert Solution
Viewing page 7 out of 8 pages
Viewing questions 301-350 out of questions