Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 7 out of 8 pages
Viewing questions 301-350 out of questions
Questions # 301:

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

Options:

A.

Determine Budget.


B.

Baseline Budget.


C.

Control Costs.


D.

Estimate Costs.


Expert Solution
Questions # 302:

Which of the following types of a dependency determination is used to define the sequence of activities?

Options:

A.

Legal


B.

Discretionary


C.

Internal


D.

Resource


Expert Solution
Questions # 303:

A procurement management plan is a subsidiary of which other type of plan?

Options:

A.

Resource plan


B.

Project management plan


C.

Cost control plan


D.

Expected monetary value plan


Expert Solution
Questions # 304:

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

Options:

A.

Control Scope


B.

Collect Requirements


C.

Create WBS


D.

Define Scope


Expert Solution
Questions # 305:

Which of the following is used as an input to prepare a cost management plan?

Options:

A.

Expert judgment


B.

Lessons learned


C.

Cost estimates


D.

Project management plan


Expert Solution
Questions # 306:

What does a CPI value greater than 1.0 indicate?

Options:

A.

Cost right at the estimated value


B.

Cost under the estimated value


C.

Cost right at the actual value


D.

Cost over the estimated value


Expert Solution
Questions # 307:

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Requested changes


B.

Approved change requests


C.

Work performance information


D.

Implemented defect repair


Expert Solution
Questions # 308:

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

Options:

A.

Bottom-up estimating


B.

Three-point estimating


C.

Analogous estimating


D.

Parametric estimating


Expert Solution
Questions # 309:

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization


B.

Change requests


C.

Validated deliverables


D.

Organizational process assets


Expert Solution
Questions # 310:

The primary benefit of the Plan Schedule Management process is that it:

Options:

A.

provides guidance to identify time or schedule challenges within the project.


B.

tightly links processes to create a seamless project schedule.


C.

guides how the project schedule will be managed throughout the project.


D.

creates an overview of all activities broken down into manageable subsections.


Expert Solution
Questions # 311:

Which scenario is most desirable during the execution phase of a project?

Options:

A.

Apply and use quality controls to ensure expectations are met throughout the project


B.

Communicate quality failures to the sponsor for feedback


C.

Conduct all quality inspections at the end of the project


D.

Only correct quality issues found if it will keep you within the budget


Expert Solution
Questions # 312:

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One


B.

Five


C.

Six


D.

Seven


Expert Solution
Questions # 313:

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

Options:

A.

Interactive communication


B.

Claims administration


C.

Conflict management


D.

Performance reporting


Expert Solution
Questions # 314:

Which activity may occur at project or phase closure?

Options:

A.

Acceptance of deliverables


B.

Change requests


C.

Project management plan updates


D.

Benchmarking


Expert Solution
Questions # 315:

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

Options:

A.

Plan Quality Management


B.

Control Quality


C.

Risk Management


D.

Plan Scope Management


Expert Solution
Questions # 316:

Question # 316

As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperforming.

What should the project manager have done to avoid this situation?

Options:

A.

Coupled inexperienced team members with individuals having extensive knowledge in the required field


B.

Had open and transparent planning that engages internal and external stakeholders


C.

Held regular meetings more often with team members to check on their progress and obstacles


D.

Diversified more of the project team to capture a broad range of experiences


Expert Solution
Questions # 317:

The following is a network diagram for a project.

The total float for the project is how many days?

Options:

A.

3


B.

5


C.

7


D.

9


Expert Solution
Questions # 318:

According to the PMI Talent Triangle. leadership skills relate to the ability to:

Options:

A.

understand the high-level overview of the organization


B.

tailor traditional and agile tools for the project


C.

work with stakeholders to develop an appropriate project delivery


D.

guide, motivate, and direct a team to reach project goals


Expert Solution
Questions # 319:

What type of change requires the submission of a change request?

Options:

A.

Changes in assigned resources


B.

Changes in a technical solution


C.

Changes in status reporting


D.

Changes in the project ' s scope


Expert Solution
Questions # 320:

Which activity is an input to the Conduct Procurements process?

Options:

A.

Organizational process assets


B.

Resource availability


C.

Perform Integrated Change Control


D.

Team performance assessment


Expert Solution
Questions # 321:

What benefit does the Manage Stakeholder Engagement process offer?

Options:

A.

Allows the project manager to increase support and minimize resistance from stakeholders


B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes


C.

Provides an actionable plan to interact effectively with stakeholders


D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders


Expert Solution
Questions # 322:

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

Options:

A.

A risk urgency assessment.


B.

The scope baseline.


C.

Work performance information.


D.

Procurement audits.


Expert Solution
Questions # 323:

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

Options:

A.

quality audits


B.

process analysis


C.

statistical sampling


D.

benchmarking


Expert Solution
Questions # 324:

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

Options:

A.

Control Quality


B.

Monitor and Control Project Work


C.

Control Scope


D.

Perform Integrated Change Control


Expert Solution
Questions # 325:

What should a project manager consider to address the full delivery life cycle for large projects?

Options:

A.

A range of techniques utilizing a plan driven approach, adaptive approach or a hybrid or both


B.

Only techniques of an agile/adaptive approach in large organizations


C.

Change the role of the project manager to managing pro|ci I in adaptive nuviionin-


D.

Splitting larger projects into two or more smaller project is which can be addressed in an adaptive method


Expert Solution
Questions # 326:

Requirements documentation will typically contain at least:

Options:

A.

Stakeholder requirements, staffing requirements, and transition requirements.


B.

Business requirements, the stakeholder register, and functional requirements.


C.

Stakeholder impact, budget requirements, and communications requirements.


D.

Business objectives, stakeholder impact, and functional requirements.


Expert Solution
Questions # 327:

What is the key benefit of the Monitor Stakeholder Engagement process?

Options:

A.

Ensures that the informational needs of the project and its stakeholders are met through implementation and the development of artifacts


B.

Ensures that the project includes all the work required and only the work required—to complete the project successfully


C.

Increases the probability and/or impact of positive risks, and decreases the probability and/or Impact of negative risks or issues


D.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves


Expert Solution
Questions # 328:

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.


B.

Acquire Project Team.


C.

Manage Project Team.


D.

Develop Project Team.


Expert Solution
Questions # 329:

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Options:

A.

List of identified risks, potential risk owners, list of potential risk response


B.

List of identified risks, list of causes, list of risk categories


C.

Short risk titles, list of potential risk owners, list of impacts on objectives


D.

List of activities affected, list of potential risk responses, list of causes


Expert Solution
Questions # 330:

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000


B.

US$9500


C.

US$10,000


D.

US$12,500


Expert Solution
Questions # 331:

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

Options:

A.

Product


B.

Cost-benefit


C.

Stakeholder


D.

Research


Expert Solution
Questions # 332:

What type of reward can hurt team cohesiveness?

Options:

A.

Sole-sum


B.

Win-lose


C.

Lose-win


D.

Partial-sum


Expert Solution
Questions # 333:

Which of the following reduces the probability of potential consequences of project risk events?

Options:

A.

Preventive action


B.

Risk management


C.

Corrective action


D.

Defect repair


Expert Solution
Questions # 334:

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Options:

A.

Planning.


B.

Executing,


C.

Monitoring and Controlling.


D.

Closing.


Expert Solution
Questions # 335:

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

Options:

A.

Schedule Variance (SV) = 2


B.

Cost Performance Index (CPI) = 0.80


C.

Schedule Performance Index (SPI) = 1.93


D.

Cost Variance (CV) = 7


Expert Solution
Questions # 336:

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs


B.

Determine Budget


C.

Estimate Costs


D.

Control Budget


Expert Solution
Questions # 337:

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

Options:

A.

Pareto


B.

Ishikawa


C.

Shewhart-Deming


D.

Delphi


Expert Solution
Questions # 338:

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

Options:

A.

Informal communication


B.

Internal communication


C.

Formal communication


D.

Horizontal communication


Expert Solution
Questions # 339:

Which document can help a project manager to leverage historical project information?

Options:

A.

Lessons learned register


B.

Schedule baseline


C.

Work performance data


D.

Deliverable acceptance forms


Expert Solution
Questions # 340:

At what stages of project should the identify Stakeholder process be performed?

Options:

A.

When beginning each phase of the project


B.

At the beginning of the project only


C.

Only when the project manager is concerned about stakeholder satisfaction


D.

When the project charter is produced, at the beginning of each phase, and when significant changes occur


Expert Solution
Questions # 341:

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Options:

A.

Continuous improvement.


B.

Predictive planning.


C.

Progressive elaboration.


D.

Quality assurance.


Expert Solution
Questions # 342:

An output of the Perform Integrated Change Control process is:

Options:

A.

Deliverables.


B.

Validated changes.


C.

The change log.


D.

The requirements traceability matrix.


Expert Solution
Questions # 343:

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation


B.

organizational theory


C.

meeting


D.

networking


Expert Solution
Questions # 344:

Which of the following Project Communication Management processes uses performance reports as an input?

Options:

A.

Manage Stakeholder Expectations


B.

Report Performance


C.

Distribute Information


D.

Plan Communications


Expert Solution
Questions # 345:

Sensitivity analysis is typically displayed as a/an:

Options:

A.

Decision tree diagram.


B.

Tornado diagram.


C.

Pareto diagram.


D.

Ishikawa diagram.


Expert Solution
Questions # 346:

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:

A.

Plan Schedule Management.


B.

Develop Project Charter.


C.

Develop Schedule.


D.

Plan Scope Management.


Expert Solution
Questions # 347:

The process of prioritizing risks for further analysis or action is known as:

Options:

A.

Plan Risk Management.


B.

Plan Risk Responses.


C.

Perform Qualitative Risk Analysis.


D.

Perform Quantitative Risk Analysis.


Expert Solution
Questions # 348:

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Options:

A.

Acquire Resources


B.

Control Resources


C.

Manage Team


D.

Develop Team


Expert Solution
Questions # 349:

Which process is engaged when a proiect learn inember makes a change to project budget with the project manager ' s approval?

Options:

A.

Manage Cost Plan


B.

Estimate Costs


C.

Determine Budget


D.

Control Costs


Expert Solution
Questions # 350:

An input to Close Project or Phase is:

Options:

A.

Accepted deliverables,


B.

Final products or services,


C.

Document updates,


D.

Work performance information.


Expert Solution
Viewing page 7 out of 8 pages
Viewing questions 301-350 out of questions