Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 7 out of 8 pages
Viewing questions 301-350 out of questions
Questions # 301:

Among all of the key stakeholders in an agile project, who is responsible for creating project requirements for the team?

Options:

A.

Scrum master


B.

Project manager


C.

Business analyst


D.

Project management office


Expert Solution
Questions # 302:

What is an output of the plan resource management process

Options:

A.

Project charter


B.

Risk register


C.

Scope baseline


D.

Stakeholder register


Expert Solution
Questions # 303:

During which process does the project team receive bids and proposals?

Options:

A.

Conduct Procurements


B.

Plan Procurements


C.

Estimate Costs


D.

Control Budget


Expert Solution
Questions # 304:

Which project performance domain is the work breakdown structure (WBS) developed?

Options:

A.

Development approach and life cycle


B.

Delivery performance


C.

Project work


D.

Planning


Expert Solution
Questions # 305:

What are the objectives of Initiation processes?

Options:

A.

Initiation processes are performed in order to develop the project charier and Identify stakeholders.


B.

Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.


C.

Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders ' goals.


D.

Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.


Expert Solution
Questions # 306:

In project management, which document is used to start the initial risk identification?

Options:

A.

Assumption log


B.

Risk management plan


C.

Risk register


D.

Issue log


Expert Solution
Questions # 307:

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.

Estimate Costs


B.

Control Costs


C.

Plan Cost Management


D.

Determine Budget


Expert Solution
Questions # 308:

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives ' ?

Options:

A.

Executing


B.

Planning


C.

Initiating


D.

Monitoring and Controlling


Expert Solution
Questions # 309:

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project ' s:

Options:

A.

Level of control.


B.

Communication channels.


C.

Scope.


D.

Strategic alignment.


Expert Solution
Questions # 310:

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor


B.

After lessons learned have been documented in contract closure


C.

When the project objectives have been met


D.

After resources have been released


Expert Solution
Questions # 311:

Which process occurs within the Monitoring and Controlling Process Group?

Options:

A.

Control Costs


B.

Plan Quality


C.

Perform Quantitative Risk Analysis


D.

Determine Budget


Expert Solution
Questions # 312:

The diagram below is an example of a:

Options:

A.

Risk breakdown structure (RBS).


B.

Project team.


C.

SWOT Analysis.


D.

Work breakdown structure (WBS).


Expert Solution
Questions # 313:

The scope of a project cannot be defined without some basic understanding of how to create the specified:

Options:

A.

objectives


B.

schedule


C.

product


D.

approach


Expert Solution
Questions # 314:

What are the formal and informal policies, procedures, and guidelines that could impact how the project ' s scope is managed?

Options:

A.

Organizational process assets


B.

Enterprise environmental factors


C.

Project management processes


D.

Project scope management plan


Expert Solution
Questions # 315:

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.


B.

statistical sampling.


C.

management responsibility,


D.

continuous improvement.


Expert Solution
Questions # 316:

An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two)

Options:

A.

Daily scrum


B.

Increments


C.

Sprint retrospective


D.

Sprint backlog


E.

Product backlog


Expert Solution
Questions # 317:

What is main purpose of Project Quantity Management?

Options:

A.

To meet customer requirements by overworking the team


B.

To fulfill project schedule objectives by rushing planned inspections


C.

To fulfill project requirements of both quality and grade


D.

To exceed customer expectations


Expert Solution
Questions # 318:

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

Options:

A.

stakeholder management strategy.


B.

communications management plan,


C.

stakeholder register,


D.

performance report.


Expert Solution
Questions # 319:

The zero duration of milestones in project planning occurs because milestones:

Options:

A.

Are unpredictable and challenge the Plan Schedule Management process.


B.

Occur at random times in the project plans.


C.

Represent a moment in time such as a significant project point or event.


D.

Represent both significant and insignificant points in the project and are difficult to anticipate.


Expert Solution
Questions # 320:

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

Options:

A.

End user


B.

Product owner


C.

Subject matter experts (SMEs)


D.

Project sponsor


E.

Project team


Expert Solution
Questions # 321:

Which tasks should a project manager accomplish in order to manage project scope correctly?

Options:

A.

Define. Validate, and Control Scope. Control Schedule; Control Costs and Manage Stakeholder Engagement


B.

Collect Requirements. Define Scope. Create WBS. Develop Schedule, and Manage Stakeholder Engagement


C.

Plan Scope Management; Collect Requirements; Define. Validate, and Control Scope; and Create WBS


D.

Define. Validate, and Control Scope. Control Costs. Manage Stakeholder Engagement, and keep budget under control


Expert Solution
Questions # 322:

A project manager is creating a project charter to provide a direct link between the project and the organization ' s strategic objectives. What must be considered when creating this document?

Options:

A.

High-level requirements and the project team


B.

Key stakeholder list and contingency reserve


C.

Detailed milestone schedule and project objectives


D.

Project purpose and high-level project description


Expert Solution
Questions # 323:

During the project life cycle for a major product, a stakeholder asked to add a new feature. Which document should they consult for guidance?

Options:

A.

Product release plan


B.

Project release plan


C.

Project management plan


D.

Product management plan


Expert Solution
Questions # 324:

A business case is being assembled. Which two elements are necessary to complete this process? (Choose two)

Options:

A.

Project management plan


B.

Product roadmap


C.

Requirements traceability matrix


D.

Business goals and objectives


E.

Risk register


Expert Solution
Questions # 325:

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Options:

A.

Customer request


B.

Market demand


C.

Technological advance


D.

Strategic opportunity


Expert Solution
Questions # 326:

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

Options:

A.

Business case


B.

Work breakdown structure


C.

Requirements documentation


D.

Risk register


Expert Solution
Questions # 327:

Which statement about identification and engagement of stakeholders during a project is correct?

Options:

A.

Project stakeholders should be Identified and engaged in every phase of the project to influence the success of the project directly.


B.

Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.


C.

Project stakeholders should be identified when the project chatter is being completed and engaged during requirements gathering.


D.

Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process.


Expert Solution
Questions # 328:

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence


B.

Value of each possible outcome multiplied by probability of non-occurrence


C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together


D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together


Expert Solution
Questions # 329:

A company is moving from a predictive to an adaptive approach. How should the company now translate the already planned work breakdown structure (WBS) to adaptive iterations?

Options:

A.

Create a product backlog with the information depicted in the WBS and prioritize the newly developed user stories into iterations.


B.

Accept this limitation and perform accordingly since the WBS can only be used in Scrum iterations.


C.

Consider reforming the structure of the company first as it is difficult for a company to transition from predictive to adaptive methods.


D.

Save the WBS in the historical data as the information can only be used for educational purposes and not as inputs for creating user stories.


Expert Solution
Questions # 330:

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

Options:

A.

Work breakdown structure


B.

Requirements document


C.

Project charter


D.

Project management plan


Expert Solution
Questions # 331:

Which input will be used when tasked with developing the human resource plan?

Options:

A.

Project management plan


B.

Activity resource requirements


C.

Resource calendar


D.

Project staff assignments


Expert Solution
Questions # 332:

During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?

Options:

A.

It is calculated incorrectly, as it cannot be zero for an in-flight project; otherwise the project is completed.


B.

Change it to a negative value to show that the project is falling behind.


C.

Zero is a perfectly valid value for an in-flight project; hence share the zero value with the stakeholder.


D.

Change it to a positive value to show that the project is ahead of its baseline schedule.


Expert Solution
Questions # 333:

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment


B.

Roles and responsibilities


C.

Staffing management plan


D.

Enterprise environmental factors


Expert Solution
Questions # 334:

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

Options:

A.

Complete project phase


B.

Project life


C.

The project life cycle


D.

Project cycle


Expert Solution
Questions # 335:

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

Options:

A.

Start-to-start (SS)


B.

Start-to-finish (SF)


C.

Rnish-to-finish (FF)


D.

Finish-to-start (FS)


Expert Solution
Questions # 336:

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.


B.

project management plan updates.


C.

change requests.


D.

work performance information.


Expert Solution
Questions # 337:

After Define Activities and Sequence Activities, the next process is:

Options:

A.

Estimate Activity Resources.


B.

Estimate Activity Durations,


C.

Develop Schedule.


D.

Control Schedule.


Expert Solution
Questions # 338:

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

Options:

A.

The customer and functional managers


B.

The risk owners and stakeholders


C.

The sponsors and stakeholders


D.

The project management team


Expert Solution
Questions # 339:

A project manager is reviewing a past project with similar.... team choosing for tailoring?

A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?

Options:

A.

Policy compliance and auditing


B.

Standards and compliance


C.

Review of lessons learned


D.

Test and inspection planning


Expert Solution
Questions # 340:

The definition of operations is a/an:

Options:

A.

organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.


B.

temporary endeavor undertaken to create a unique product, service, or result.


C.

organization that provides oversight for an administrative area.


D.

organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.


Expert Solution
Questions # 341:

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating


B.

Planning


C.

Executing


D.

Monitoring and Controlling


Expert Solution
Questions # 342:

The completion of the project scope is measured against the:

Options:

A.

requirements documentation.


B.

project scope statement.


C.

project management plan.


D.

work performance measurements.


Expert Solution
Questions # 343:

What kind of skills should a project manager use when attempting to achieve consensus by balancing the conflicting and competing goals of project stakeholders?

Options:

A.

Interpersonal skills and the ability to manage people


B.

Strategic and business management skills


C.

Technical and business management skills


D.

Business analysis skills and expertise


Expert Solution
Questions # 344:

In a typical project, project managers spend most of their time:

Options:

A.

Estimating


B.

Scheduling


C.

Controlling


D.

Communicating


Expert Solution
Questions # 345:

What are the key tools for managing project knowledge?

Options:

A.

Expert judgment and data gathering


B.

Networking and storytelling


C.

Data analysis and decision making


D.

Prototypes and product analysis


Expert Solution
Questions # 346:

Which of the following is a tool and technique used in the Develop Schedule process?

Options:

A.

Three-point estimates


B.

Resource leveling


C.

Precedence diagramming method


D.

Bottom-up estimating


Expert Solution
Questions # 347:

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

Options:

A.

2.0


B.

45


C.

0.5


D.

15


Expert Solution
Questions # 348:

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

Options:

A.

Engage customer earlier


B.

Conduct quality audits


C.

Validate Scope


D.

Validate quality requirements


Expert Solution
Questions # 349:

Which project documents can determine the budget?

Options:

A.

Procurement documents, contracts, requirements documentation, and basis of estimates


B.

Basis of estimates, cost estimates, project schedule, and risk register


C.

Business case, project charter, statement of work, and cost estimates


D.

Scope baseline, resource management plan, activity list, and assumption log


Expert Solution
Questions # 350:

Which activity is an input to the Conduct Procurements process?

Options:

A.

Organizational process assets


B.

Resource availability


C.

Perform Integrated Change Control


D.

Team performance assessment


Expert Solution
Viewing page 7 out of 8 pages
Viewing questions 301-350 out of questions