New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 7 out of 8 pages
Viewing questions 301-350 out of questions
Questions # 301:

A required input for Create WBS is a project:

Options:

A.

quality plan.


B.

schedule network.


C.

management document update.


D.

scope statement.


Expert Solution
Questions # 302:

Which of the following is an input to Control Scope?

Options:

A.

Project schedule


B.

Organizational process assets updates


C.

Project document updates


D.

Work performance information


Expert Solution
Questions # 303:

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional


B.

Projectized


C.

Matrix


D.

Balanced


Expert Solution
Questions # 304:

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational breakdown structure (OBS)


B.

Work performance information


C.

Work package


D.

Work breakdown structure (WBS)


Expert Solution
Questions # 305:

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis


B.

Make or buy analysis


C.

Contract value analysis


D.

Cost impact analysis


Expert Solution
Questions # 306:

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

Options:

A.

Three weeks


B.

Four weeks


C.

Five weeks


D.

Six weeks


Expert Solution
Questions # 307:

A tool or technique in Perform Quality Control that a project manager would use is:

Options:

A.

quality audits.


B.

process analysis.


C.

benchmarking.


D.

inspection.


Expert Solution
Questions # 308:

What does a CPI value greater than 1.0 indicate?

Options:

A.

Cost right at the estimated value


B.

Cost under the estimated value


C.

Cost right at the actual value


D.

Cost over the estimated value


Expert Solution
Questions # 309:

In which process is a project manager identified and given the authority to apply resources to project activities?

Options:

A.

Acquire Project Team


B.

Develop Project Management Plan


C.

Manage Project Execution


D.

Develop Project Charter


Expert Solution
Questions # 310:

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

Options:

A.

Work performance information.


B.

Inspections and audits.


C.

Payment systems.


D.

Procurement performance reviews.


Expert Solution
Questions # 311:

Which input to the Plan Risk Management process provides information on high-level risks?

Options:

A.

Project charter


B.

Enterprise environmental factors


C.

Stakeholder register


D.

Organizational process assets


Expert Solution
Questions # 312:

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory


B.

Discretionary


C.

Internal


D.

External


Expert Solution
Questions # 313:

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.


B.

Performance reporting.


C.

Bidder conferences.


D.

Reserve analysis.


Expert Solution
Questions # 314:

Typical outcomes of a project include:

Options:

A.

Products, services, and improvements.


B.

Products, programs, and services.


C.

Improvements, portfolios, and services.


D.

Improvements, processes, and products.


Expert Solution
Questions # 315:

A technique used to determine the cause and degree of difference between baseline and actual performance is:

Options:

A.

Product analysis.


B.

Variance analysis.


C.

Document analysis,


D.

Decomposition.


Expert Solution
Questions # 316:

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:

A.

Project Communications Management


B.

Project Integration Management


C.

Project Risk Management


D.

Project Scope Management


Expert Solution
Questions # 317:

Which document describes the necessary information to determine if a project is worth the required investment?

Options:

A.

Cost baseline


B.

Service level agreement


C.

Memorandum of understanding


D.

Business case


Expert Solution
Questions # 318:

Identify Risks is part of which Process Group?

Options:

A.

Planning


B.

Executing


C.

Closing


D.

Initiating


Expert Solution
Questions # 319:

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan


B.

Stakeholder register


C.

Risk log


D.

Communications management plan


Expert Solution
Questions # 320:

Which process numerically analyzes the effect of identified risks on overall project objectives?

Options:

A.

Plan Risk Management


B.

Plan Risk Responses


C.

Perform Quantitative Risk Analysis


D.

Perform Qualitative Risk Analysis


Expert Solution
Questions # 321:

Which cost is associated with nonconformance?

Options:

A.

Liabilities


B.

Inspections


C.

Training


D.

Equipment


Expert Solution
Questions # 322:

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

Options:

A.

Identify Risks


B.

Control Risks


C.

Perform Quantitative Risk Analysis


D.

Perform Qualitative Risk Analysis


Expert Solution
Questions # 323:

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

Options:

A.

Enhance


B.

Share


C.

Exploit


D.

Accept


Expert Solution
Questions # 324:

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Options:

A.

Facilitation techniques


B.

Expert judgment


C.

Analytical techniques


D.

Variance analysis


Expert Solution
Questions # 325:

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

Options:

A.

Bottom-up


B.

Parametric


C.

Analogous


D.

Three-point


Expert Solution
Questions # 326:

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

Options:

A.

A risk urgency assessment.


B.

The scope baseline.


C.

Work performance information.


D.

Procurement audits.


Expert Solution
Questions # 327:

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning


B.

At the beginning and the end


C.

Once during each phase


D.

Repeatedly


Expert Solution
Questions # 328:

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Options:

A.

Stakeholder register


B.

Scope management plan


C.

Stakeholder management plan


D.

Project charter


Expert Solution
Questions # 329:

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Options:

A.

Procurement documents


B.

Communications plan


C.

Project charter


D.

Stakeholder register


Expert Solution
Questions # 330:

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope


B.

Define Scope


C.

Plan Scope Management


D.

Collect Requirements


Expert Solution
Questions # 331:

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

Options:

A.

Develop Project Team.


B.

Manage Project Team.


C.

Acquire Project Team.


D.

Plan Human Resource Management.


Expert Solution
Questions # 332:

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Options:

A.

Planning.


B.

Executing,


C.

Monitoring and Controlling.


D.

Closing.


Expert Solution
Questions # 333:

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

Options:

A.

Work packages.


B.

Accepted deliverables.


C.

The WBS dictionary.


D.

The scope baseline.


Expert Solution
Questions # 334:

The number of potential communication channels for a project with 5 stakeholders is:

Options:

A.

10.


B.

12.


C.

20.


D.

24.


Expert Solution
Questions # 335:

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan


B.

Project charter


C.

Project management plan


D.

Service level agreement


Expert Solution
Questions # 336:

Which tools or techniques are used in the Plan Schedule Management process?

Options:

A.

Benchmarking, expert judgment, and analytical techniques


B.

Statistical sampling, benchmarking, and meetings


C.

Negotiations, pre-assignment, and multi-criteria decision analysis


D.

Expert judgment, analytical techniques, and meetings


Expert Solution
Questions # 337:

An output of the Plan Quality Management process is:

Options:

A.

A process improvement plan,


B.

Quality control measurements.


C.

Work performance information,


D.

The project management plan.


Expert Solution
Questions # 338:

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.


B.

Acquire Project Team.


C.

Manage Project Team.


D.

Develop Project Team.


Expert Solution
Questions # 339:

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

Options:

A.

Collect Requirements.


B.

Conduct Procurements.


C.

Estimate Activity Durations.


D.

Estimate Activity Resources.


Expert Solution
Questions # 340:

A temporary endeavor that creates a unique product or service is called a:

Options:

A.

Project


B.

Plan


C.

Program


D.

Portfolio


Expert Solution
Questions # 341:

Plan Schedule Management is a process in which Knowledge Area?

Options:

A.

Project Scope Management


B.

Project Human Resource Management


C.

Project Integration Management


D.

Project Time Management


Expert Solution
Questions # 342:

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

Options:

A.

Human resource management plan.


B.

Activity resource requirements.


C.

Personnel assessment tools,


D.

Multi-criteria decision analysis.


Expert Solution
Questions # 343:

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique


B.

Idea/mind mapping


C.

Affinity diagram


D.

Brainstorming


Expert Solution
Questions # 344:

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

Options:

A.

Interrelationship digraphs


B.

Tree diagram


C.

Affinity diagram


D.

Network diagram


Expert Solution
Questions # 345:

The Perform Integrated Change Control process occurs in which Process Group?

Options:

A.

Initiating


B.

Executing


C.

Monitoring and Controlling


D.

Planning


Expert Solution
Questions # 346:

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Options:

A.

Identify Risks


B.

Control Risks


C.

Plan Risk Management


D.

Plan Risk Responses


Expert Solution
Questions # 347:

Which tool or technique is used to develop the human resource management plan?

Options:

A.

Ground rules


B.

Expert judgment


C.

Team-building activities


D.

Interpersonal skills


Expert Solution
Questions # 348:

The process of defining how the project scope will be validated and controlled is known as:

Options:

A.

Define Scope.


B.

Develop Project Management Plan.


C.

Plan Scope Management.


D.

Plan Quality Management.


Expert Solution
Questions # 349:

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

Options:

A.

Technical approach


B.

Technical capability


C.

Business size and type


D.

Production capacity and interest


Expert Solution
Questions # 350:

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Options:

A.

Update


B.

Preventive action


C.

Defect repair


D.

Corrective action


Expert Solution
Viewing page 7 out of 8 pages
Viewing questions 301-350 out of questions