CAPM Exam Topic 34 Question 339 Discussion:
Question #: 339
Topic #: 34

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:


A.

Collect Requirements.


B.

Conduct Procurements.


C.

Estimate Activity Durations.


D.

Estimate Activity Resources.