PMI Certified Associate in Project Management (CAPM) CAPM Question # 336 Topic 34 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 336 Topic 34 Discussion

CAPM Exam Topic 34 Question 336 Discussion:
Question #: 336
Topic #: 34

Which tools or techniques are used in the Plan Schedule Management process?


A.

Benchmarking, expert judgment, and analytical techniques


B.

Statistical sampling, benchmarking, and meetings


C.

Negotiations, pre-assignment, and multi-criteria decision analysis


D.

Expert judgment, analytical techniques, and meetings