PMI Certified Associate in Project Management (CAPM) CAPM Question # 336 Topic 34 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 336 Topic 34 Discussion

CAPM Exam Topic 34 Question 336 Discussion:
Question #: 336
Topic #: 34

A few project team members are having issues understanding the requirements as described. Which action should be taken to resolve this issue?


A.

Review the requirements traceability matrix and set up a meeting with the business analyst and key stakeholders.


B.

Review the requirements traceability matrix, the business analysis communications management plan, and set up a meeting with the business analyst and key stakeholders.


C.

Review the business analysis communications management plan and set up a meeting with the business analyst and key stakeholders.


D.

Review the project management plan and set up a meeting with the project manager and key stakeholders.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.