Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 338 Topic 34 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 338 Topic 34 Discussion

CAPM Exam Topic 34 Question 338 Discussion:
Question #: 338
Topic #: 34

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?


A.

Informal communication


B.

Internal communication


C.

Formal communication


D.

Horizontal communication


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.