Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 338 Topic 34 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 338 Topic 34 Discussion

CAPM Exam Topic 34 Question 338 Discussion:
Question #: 338
Topic #: 34

A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?


A.

Forward the status reports to the stakeholder.


B.

Manage stakeholder engagement.


C.

Consult the communications management plan.


D.

Update the communications management plan.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.