PMI Certified Associate in Project Management (CAPM) CAPM Question # 328 Topic 33 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 328 Topic 33 Discussion

CAPM Exam Topic 33 Question 328 Discussion:
Question #: 328
Topic #: 33

The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy?


A.

Payment types, delivery methods, and procurement phases


B.

Procurement metrics, make-or-buy decisions, and procurement statement of work


C.

Vendor selection criteria, stakeholder roles and responsibilitys, and prequalified sellers


D.

Timetable procurement activities, product cost, and knowledge transfer schedule


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.