PMI Certified Associate in Project Management (CAPM) CAPM Question # 327 Topic 33 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 327 Topic 33 Discussion

CAPM Exam Topic 33 Question 327 Discussion:
Question #: 327
Topic #: 33

Which baselines make up the performance measurement baseline?


A.

Scope baseline, cost baseline, and schedule baseline


B.

Scope baseline, project management baseline, and quality baseline


C.

Cost baseline, schedule baseline, and risk baseline


D.

Cost baseline, project management baseline, and schedule baseline


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.