New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 326 Topic 33 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 326 Topic 33 Discussion

CAPM Exam Topic 33 Question 326 Discussion:
Question #: 326
Topic #: 33

The basis of identification for current or potential problems to support later claims or new procurements is provided by:


A.

A risk urgency assessment.


B.

The scope baseline.


C.

Work performance information.


D.

Procurement audits.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.