Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 326 Topic 33 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 326 Topic 33 Discussion

CAPM Exam Topic 33 Question 326 Discussion:
Question #: 326
Topic #: 33

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?


A.

-8


B.

425


C.

1.4


D.

8


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.