CAPM Exam Topic 33 Question 325 Discussion:
Question #: 325
Topic #: 33

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?


A.

Bottom-up


B.

Parametric


C.

Analogous


D.

Three-point