CAPM Exam Topic 33 Question 324 Discussion:
Question #: 324
Topic #: 33

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?


A.

Matrix - strong


B.

Matrix - balanced


C.

Virtual


D.

Functional