PMI Certified Associate in Project Management (CAPM) CAPM Question # 308 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 308 Topic 31 Discussion

CAPM Exam Topic 31 Question 308 Discussion:
Question #: 308
Topic #: 31

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?


A.

Develop consensus among stakeholders


B.

Get the budget approved for change


C.

Make sure management is aware of the change


D.

Get approval from the change control board


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.