New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 308 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 308 Topic 31 Discussion

CAPM Exam Topic 31 Question 308 Discussion:
Question #: 308
Topic #: 31

What does a CPI value greater than 1.0 indicate?


A.

Cost right at the estimated value


B.

Cost under the estimated value


C.

Cost right at the actual value


D.

Cost over the estimated value


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.