Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 308 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 308 Topic 31 Discussion

CAPM Exam Topic 31 Question 308 Discussion:
Question #: 308
Topic #: 31

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?


A.

Bottom-up estimating


B.

Three-point estimating


C.

Analogous estimating


D.

Parametric estimating


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.