New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 309 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 309 Topic 31 Discussion

CAPM Exam Topic 31 Question 309 Discussion:
Question #: 309
Topic #: 31

In which process is a project manager identified and given the authority to apply resources to project activities?


A.

Acquire Project Team


B.

Develop Project Management Plan


C.

Manage Project Execution


D.

Develop Project Charter


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.