PMI Certified Associate in Project Management (CAPM) CAPM Question # 309 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 309 Topic 31 Discussion

CAPM Exam Topic 31 Question 309 Discussion:
Question #: 309
Topic #: 31

A company is moving from a predictive to an adaptive approach. How should the company now translate the already planned work breakdown structure (WBS) to adaptive iterations?


A.

Create a product backlog with the information depicted in the WBS and prioritize the newly developed user stories into iterations.


B.

Accept this limitation and perform accordingly since the WBS can only be used in Scrum iterations.


C.

Consider reforming the structure of the company first as it is difficult for a company to transition from predictive to adaptive methods.


D.

Save the WBS in the historical data as the information can only be used for educational purposes and not as inputs for creating user stories.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.