PMI Certified Associate in Project Management (CAPM) CAPM Question # 310 Topic 32 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 310 Topic 32 Discussion

CAPM Exam Topic 32 Question 310 Discussion:
Question #: 310
Topic #: 32

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?


A.

Add more risk categories


B.

Identify, analyze, and manage risk during each iteration of the project


C.

Add new values to the probability and impact matrix


D.

Increase the reserves because of the high variability environment


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.