Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 335 Topic 34 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 335 Topic 34 Discussion

CAPM Exam Topic 34 Question 335 Discussion:
Question #: 335
Topic #: 34

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?


A.

Start-to-start (SS)


B.

Start-to-finish (SF)


C.

Rnish-to-finish (FF)


D.

Finish-to-start (FS)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.