PMI Certified Associate in Project Management (CAPM) CAPM Question # 335 Topic 34 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 335 Topic 34 Discussion

CAPM Exam Topic 34 Question 335 Discussion:
Question #: 335
Topic #: 34

In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?


A.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.


B.

Make sure proper testing gets completed to minimize the risk highlighted.


C.

Add this risk to the lessons learned register on project completion.


D.

Add the stakeholder to the stakeholder register and add the risk to the risk register.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.