Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 335 Topic 34 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 335 Topic 34 Discussion

CAPM Exam Topic 34 Question 335 Discussion:
Question #: 335
Topic #: 34

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?


A.

Schedule Variance (SV) = 2


B.

Cost Performance Index (CPI) = 0.80


C.

Schedule Performance Index (SPI) = 1.93


D.

Cost Variance (CV) = 7


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.