CAPM Exam Topic 32 Question 318 Discussion
PMI Certified Associate in Project Management (CAPM) CAPM Question # 318 Topic 32 Discussion
PMI Discussions
Browse All Questions
Go to Exam Detail
Get Premium Access
Previous
Next
PMI Certified Associate in Project Management (CAPM) CAPM Question # 318 Topic 32 Discussion
CAPM Exam Topic 32 Question 318 Discussion:
Question #:
318
Topic #:
32
Identify Risks is part of which Process Group?
A.
Planning
B.
Executing
C.
Closing
D.
Initiating
Show Answer
Get Premium CAPM Questions
Answer
Correct Answer:
A
Options Selected by Other Users:
Option A:
(84 votes)
82.35%
Option B:
(14 votes)
13.73%
Option C:
(4 votes)
3.92%
Option D:
(0 votes)
0%
Contribute your Thoughts:
Chosen Answer:
A
B
C
D
This is a voting comment
(
?
)
.
You can switch to a
simple comment
.
It is better to Upvote an existing comment if you don't have anything to add.
Maximum 400 character.
Submit
Awaiting moderator approval
Previous
Next
Modal title
×
Registered Required
×
In order to participate in the comments you need to be logged-in.
You can
sign-up
or
login
(it's free).
Submit