New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 319 Topic 32 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 319 Topic 32 Discussion

CAPM Exam Topic 32 Question 319 Discussion:
Question #: 319
Topic #: 32

A project manager should document the escalation path for unresolved project risks in the:


A.

Change control plan


B.

Stakeholder register


C.

Risk log


D.

Communications management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.