PMI Certified Associate in Project Management (CAPM) CAPM Question # 320 Topic 33 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 320 Topic 33 Discussion

CAPM Exam Topic 33 Question 320 Discussion:
Question #: 320
Topic #: 33

What process is performed periodically throughout the project as needed?


A.

Plan Risk Management


B.

Plan Communications Management


C.

Plan Resource Management


D.

Plan Cost Management


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.