PMI Certified Associate in Project Management (CAPM) CAPM Question # 346 Topic 35 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 346 Topic 35 Discussion

CAPM Exam Topic 35 Question 346 Discussion:
Question #: 346
Topic #: 35

What is one of the objectives of Project Risk Management?


A.

Decrease the probability and impact of an event on project objectives.


B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.


C.

Increase the probability and impact of positive events.


D.

Removal of project risk.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.