Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 346 Topic 35 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 346 Topic 35 Discussion

CAPM Exam Topic 35 Question 346 Discussion:
Question #: 346
Topic #: 35

A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?


A.

Review the project management plan.


B.

Share the requirements traceability matrix the same way it was shared previously.


C.

Consult the business analysis communications management plan.


D.

Ask the project manager to share the updated requirements traceability matrix at the next meeting.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.