Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 347 Topic 35 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 347 Topic 35 Discussion

CAPM Exam Topic 35 Question 347 Discussion:
Question #: 347
Topic #: 35

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.


A.

2.0


B.

45


C.

0.5


D.

15


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.