CAPM Exam Topic 35 Question 348 Discussion:
Question #: 348
Topic #: 35

The process of defining how the project scope will be validated and controlled is known as:


A.

Define Scope.


B.

Develop Project Management Plan.


C.

Plan Scope Management.


D.

Plan Quality Management.