CAPM Exam Topic 35 Question 348 Discussion:
Question #: 348
Topic #: 35

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?


A.

Engage customer earlier


B.

Conduct quality audits


C.

Validate Scope


D.

Validate quality requirements