Question #: 349
Topic #: 35

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?


A.

Technical approach


B.

Technical capability


C.

Business size and type


D.

Production capacity and interest