New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 350 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 350 Topic 36 Discussion

CAPM Exam Topic 36 Question 350 Discussion:
Question #: 350
Topic #: 36

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?


A.

Update


B.

Preventive action


C.

Defect repair


D.

Corrective action


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.