Question #: 351
Topic #: 36

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?


A.

One


B.

Five


C.

Six


D.

Seven