A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:


A.

Historical information and the lessons-learned database.


B.

Historical information and the stakeholder register.


C.

Organizational process assets and the lessons-learned database.


D.

Project documents and historical information.