CAPM Exam Topic 36 Question 352 Discussion:
Question #: 352
Topic #: 36

Which of the following lists represents the outputs of the Monitor Communications process?


A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates


B.

Work performance information, change requests, project management plan updates, and project documents updates


C.

Communications management plan, project management plan updates, work performance report, and project documents update


D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates