PMI Certified Associate in Project Management (CAPM) CAPM Question # 353 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 353 Topic 36 Discussion

CAPM Exam Topic 36 Question 353 Discussion:
Question #: 353
Topic #: 36

Which are examples of processes that may be used once or at predefined points in the project life cycle?


A.

Develop Project Charter and Close Project or Phase


B.

Define Activities and Acquire Resources


C.

Control Schedule and Conduct Procurements


D.

Monitor Communications and Control Costs


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.