PMI Certified Associate in Project Management (CAPM) CAPM Question # 353 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 353 Topic 36 Discussion

CAPM Exam Topic 36 Question 353 Discussion:
Question #: 353
Topic #: 36

An output of the Create WBS process is:


A.

Scope baseline.


B.

Project scope statement.


C.

Organizational process assets.


D.

Requirements traceability matrix.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.