PMI Certified Associate in Project Management (CAPM) CAPM Question # 354 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 354 Topic 36 Discussion

CAPM Exam Topic 36 Question 354 Discussion:
Question #: 354
Topic #: 36

In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?


A.

Involvement is needed only during project initiation.


B.

Minimal involvement of stakeholders is sufficient.


C.

They should be continuously engaged.


D.

They should be involved only during phase or deliverable reviews.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.