PMI Certified Associate in Project Management (CAPM) CAPM Question # 355 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 355 Topic 36 Discussion

CAPM Exam Topic 36 Question 355 Discussion:
Question #: 355
Topic #: 36

A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?


A.

A diagram in which resource optimization has been applied.


B.

A diagram in which the critical path method has been applied.


C.

A diagram in which a predefined series of activities has been organized.


D.

A diagram which shows a combination of resource and time optimization.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.