A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
A.
A diagram in which resource optimization has been applied.
B.
A diagram in which the critical path method has been applied.
C.
A diagram in which a predefined series of activities has been organized.
D.
A diagram which shows a combination of resource and time optimization.