CAPM Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

The probability and impact matrix is primarily used to:


A.

Quantify risk issues for trends during a quality audit.


B.

Develop a risk register for risk planning.


C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.


D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.